Introduction
Building Information Modelling has been discussed in the construction industry for years. For a long time, BIM was often associated with 3D modelling, clash detection and software such as Revit, Navisworks and Civil 3D. Those tools are still important, but Ireland is now moving towards something much broader.
Since January 2024, Building Information Modelling requirements have been progressively introduced into Ireland's Capital Works Management Framework (CWMF). The Government's approach is not simply asking project teams to produce models. It is introducing a structured approach to managing information throughout the delivery and lifecycle of public assets, with ISO 19650 at the centre of that process.
This is a significant change for the Irish construction and infrastructure sector.
The question is therefore no longer whether BIM is coming to Ireland. It is already here. The more important question is whether organisations understand what the mandate actually requires and, more importantly, what ISO 19650 means for the way projects are planned, designed, constructed and eventually operated. For me, this is where the conversation around BIM needs to mature.
Ireland's BIM mandate is already being implemented
The Irish Government's BIM adoption strategy was introduced through the CWMF, with requirements beginning on 1 January 2024 for design teams working on public works contracts valued above €100 million. The requirements are then being progressively extended to smaller projects and to contractors and the supply chain.
The rollout is deliberately phased.
From January 2024, design teams on projects above €100 million came into scope. From January 2025, contractors and supply chains on those projects were included, while design teams on projects above €20 million also entered the requirements. By January 2026, contractor and supply-chain requirements had extended to projects above €10 million.
As of July 2026, design teams on projects above €5 million are within the mandate. From January 2027, contractors and their supply chains on projects above €5 million will follow, with the requirements then moving down to projects above €1 million and ultimately projects below €1 million. By January 2028, contractor and supply-chain requirements will apply to projects below €1 million as well. In other words, the direction of travel is very clear. BIM requirements are moving from major public projects into the mainstream of public works delivery.
The Government has described the strategy as part of its wider ambition to digitalise the construction sector by 2030. Build Digital, which was established by Government in 2021 to support digital transformation in the Irish construction and built environment sector, has also been tasked with helping organisations develop the capability to meet these requirements. Minister Paschal Donohoe previously described the purpose of the BIM requirements in practical terms, stating that BIM can help deliver projects "to a higher quality and safety level, reduces waste and can deliver projects in a more timely manner."
That is important because it shows that the Government's objective is not BIM for BIM's sake. The intention is to use digital information to improve the way public projects are delivered.
So what exactly is required?
The Irish BIM mandate is built around four core requirements: ISO 19650, Uniclass, Industry Foundation Classes (IFC) and the International Cost Management Standard (ICMS), each has a different purpose. ISO 19650 provides the information management framework. Uniclass provides a structured classification system. IFC supports interoperability between different BIM software platforms, while ICMS provides a structured approach to reporting project costs, including lifecycle costs and carbon.
Together, these requirements are intended to create something much more useful than a collection of models. They are intended to create consistent project information.
This distinction matters. A project can have highly detailed 3D models and still have poor information management. Files can be incorrectly named, information can be issued to the wrong people, revisions can be unclear, responsibilities can be poorly defined and important asset information can be lost during handover.
That is not effective BIM. The CWMF itself describes BIM as "a process for creating and managing information on a construction project throughout its whole life cycle."
That definition is probably one of the most important things for organisations to understand. BIM is not the model. The model is one output of the information management process.
ISO 19650 is really about information management
ISO 19650 is an international series of standards for managing information using BIM. ISO describes the framework as covering the creation, exchange, recording, versioning and organisation of information across the lifecycle of a built asset. This includes much more than design. Information management can begin during strategic planning and continue through design, procurement, construction, commissioning, operation, maintenance, refurbishment and eventually the end of the asset's life.
That is why ISO 19650 is particularly relevant to infrastructure. An infrastructure project does not stop being valuable when the contractor leaves site. The information created during design and construction can remain important for decades.
A road, bridge, water treatment plant, hospital or school needs to be operated and maintained. If the information required to manage that asset is incomplete, inaccurate or difficult to access, the problem does not disappear when the construction project closes.
It simply becomes someone else's problem.
What does this mean on an actual project?
This is where ISO 19650 becomes much more practical.
At the beginning of a project, the client needs to understand what information is actually required. This feeds into requirements such as the Organisation Information Requirements, Project Information Requirements, Asset Information Requirements and Exchange Information Requirements. Those requirements then influence how information is produced, checked, exchanged and ultimately accepted. The CWMF's own guidance recommends appointing an Information Manager and developing a structured BIM Implementation Plan aligned with ISO 19650. The Exchange Information Requirements also become an important part of the tendering and appointment process.
This changes the traditional idea that BIM is something the design team simply "does".
The client has responsibilities. The design team has responsibilities. The contractor has responsibilities. Subcontractors and suppliers increasingly have responsibilities. The information manager has responsibilities. The Common Data Environment also becomes an important part of the process because project information needs to be managed through controlled workflows rather than simply being passed around through email attachments and disconnected file systems. That is where BIM begins to look much more like quality management.
The Common Data Environment is more than a shared folder
One of the biggest misunderstandings around BIM is the idea that a Common Data Environment, or CDE, is simply a cloud folder where everyone stores their drawings and models. It is much more than that. The CDE supports the controlled management of information, including status, revision, suitability, approvals and information exchanges. It provides a structured environment in which project information can move through defined workflows.
For anyone who has worked in document control or QA/QC, the logic is familiar.
You want to know what document you are looking at, who produced it, which revision it is, whether it has been checked, whether it has been approved and whether it is suitable for the purpose for which it is being used. ISO 19650 takes that principle and applies it to a much wider digital information environment. This is one of the reasons I see such a strong connection between BIM, information management and quality management.
The objective is control.
BIM and quality management are closer than they appear
In my previous article, I argued that quality should be treated as part of the delivery system rather than something inspected at the end. The same principle applies to information. If incorrect information is allowed to move through a project, the consequences can be very similar to a physical quality failure. A wrong drawing revision can result in incorrect construction. Missing information can delay procurement. Poor coordination can create rework. Incorrect asset information can create problems during operation. This is why information quality matters.
ISO 19650 provides a framework for controlling the production and exchange of information, while ISO 9001 provides a wider quality management framework for controlling organisational processes and continually improving them. The two standards are not the same, but they can work very well together. One controls the wider quality management system. The other provides a framework for managing information within the built environment.
The Irish industry is moving, but there are still challenges
The transition is not happening without difficulties. Build Digital's 2025 annual survey, based on responses from 205 participants across industry, Government and academia, found that digital adoption continues to progress across the Irish construction sector. However, the report also identified skills gaps, uneven training provision, limited OpenBIM adoption and inconsistent implementation of ISO 19650 and CWMF BIM requirements. That is an important finding. It suggests that the challenge is no longer simply convincing people that digital construction is important. The challenge is building the capability to implement it consistently.
Build Digital's survey also indicates that 81% of participants in its most recent survey work in organisations actively engaged in digital transformation journeys. There is therefore clear movement within the industry, but digital maturity is not evenly distributed. This is understandable. BIM implementation requires investment in people, processes, standards, software and organisational change. It also requires something that is often underestimated: management commitment. Technology can be purchased relatively quickly. Developing people who understand why the process exists and how to apply it consistently takes much longer.
The industry is moving from "why" to "how"
This change in maturity was visible at the 2026 Digital Delivery for Ireland's Infrastructure event, jointly hosted by NSAI, Build Digital and the Infrastructure Division of the Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation. The event focused on proposed revisions to ISO 19650, certification pathways and real-world implementation of the Irish BIM mandate. That shift in conversation is significant. The industry is increasingly moving beyond asking why BIM matters and towards asking how organisations can implement information management effectively.
Build Digital Project Lead Robert Moore has emphasised the practical side of this transition. Discussing the organisation's Information Management Plans, he explained that they were specifically designed to be compliant with ISO 19650 and to translate the requirements of the standard into something organisations can actually apply within their businesses. That practical approach is important. Standards are useful because they provide consistency. But a standard sitting on a shelf does not improve a project.
The value comes when the standard is translated into roles, procedures, information requirements, workflows and behaviours that people actually use.
Information management is becoming a profession in its own right
Another interesting development in Ireland during 2026 has been the publication of Information Manager BIM role profiles by Build Digital, NSAI and the Infrastructure Division. The role profiles recognise that information management is not simply a technical function. They describe responsibilities around planning, managing and assuring information production and exchange, including CDE management, information requirements, PIMs, IFC outputs and alignment with ISO 19650 and the CWMF. This is a significant development. For years, BIM responsibilities could sometimes be treated as something added to an existing technical role. The Irish BIM mandate is creating a much clearer distinction between modelling and information management. That distinction will become increasingly important as projects become larger, more complex and more digitally connected.
The industry will need people who understand technology, but also people who understand processes, governance, quality, compliance and project delivery.
In my view, that combination is where the real value of information management sits.
TII shows where this is heading
Transport Infrastructure Ireland provides a good example of how this approach is being applied to infrastructure. TII is implementing a structured Information Management and BIM framework across the full lifecycle of transport infrastructure projects, aligned with the Public Sector BIM Mandate and ISO 19650. Its framework covers planning, design, construction, operation and maintenance for national roads, greenways, active travel schemes and associated infrastructure. The objective is not simply to create better models.
TII identifies improved collaboration, better information quality, safer delivery, improved asset management and data-driven decision-making as benefits of the framework.
That is exactly where I think the Irish BIM conversation needs to go. The real value of BIM is not necessarily the visualisation on a screen. It is what better information allows people to do.
The next challenge is consistency
Ireland has now created much of the structure needed for a national BIM approach.
There is a Government mandate.
There is the CWMF.
There are defined standards.
There is Build Digital.
There are industry templates and guidance.
There are Information Manager role profiles.
There is an NSAI BIM certification scheme based on ISO 19650-2.
There are major public clients such as TII implementing structured information management.
The next challenge is consistency. The question is whether organisations can take these requirements and embed them into everyday project delivery. That means moving beyond having a BIM Execution Plan because the contract requires one. It means understanding why the information requirements exist. It means making sure people use the CDE correctly. It means checking information before it is exchanged. It means ensuring subcontractors and suppliers understand what is expected of them.
Most importantly, it means connecting the digital process with the physical project.
BIM should ultimately make project delivery easier
There is a danger that BIM becomes another compliance layer. It's another template, another meeting, another document, another box to tick and that would miss the point.
Build Digital's current adoption supports emphasise that technology should be treated as an enabler of agreed processes rather than the driver itself. Its guidance focuses on people, processes, governance and repeatable workflows alongside technology and I think that is the right approach.
A well-managed BIM process should make it easier to find the right information, understand what has changed, coordinate disciplines, identify problems earlier, support procurement, manage construction and eventually operate the completed asset.
If it does not do those things, we need to question the process rather than simply buying more software.
Ireland has an opportunity to get this right
The Irish BIM mandate represents a major change in how public infrastructure projects will be delivered but the most important part of the mandate may not be the models.
It may be the culture of information management that develops around them. ISO 19650 gives Ireland a common framework. Uniclass provides structure. IFC supports interoperability. ICMS brings cost and carbon information into the wider picture. The CWMF provides the public-sector delivery framework. The opportunity now is to connect these elements.
If we do that properly, BIM becomes much more than a design technology. It becomes part of the infrastructure delivery system. That is particularly important as Ireland moves into a period of significant infrastructure investment. The country will need to deliver more projects, faster and with greater pressure on cost, resources and skills.
Better information will not solve every infrastructure problem but poor information can certainly make those problems worse.
Conclusion
The Irish BIM mandate is sometimes described as a requirement to "do BIM". I think that description is too simple. What Ireland is really doing is introducing a more structured approach to information management across public infrastructure delivery. ISO 19650 sits at the centre of that change because it moves the conversation beyond 3D models and towards the controlled creation, management, exchange and use of information throughout the asset lifecycle and that is a much bigger idea.
For organisations, the challenge is not simply buying software or producing models. It is developing the people, processes and governance needed to manage information properly. For project teams, it means understanding that information is an asset in its own right. And for Ireland, the opportunity is bigger still.
If the country can connect BIM, ISO 19650, quality management, cost management and infrastructure delivery into practical systems that people actually use, digitalisation can become more than another compliance requirement. It can become a way of delivering infrastructure better. Because ultimately, BIM is not about creating a better model.
It is about creating better information so that people can make better decisions. And better decisions are what build better infrastructure.
References
Build Digital. (2026). Build Digital annual survey 2025 and trends & comparisons 2022–2025. Technological University Dublin.
Capital Works Management Framework. (2026). Public sector BIM adoption timeline. Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation.
Capital Works Management Framework. (2026). Core BIM requirements. Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation.
Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation. (2024). Minister Donohoe publishes the Build 2024 report examining construction sector performance and capacity.
International Organization for Standardization. (2018). ISO 19650-1:2018: Organization and digitization of information about buildings and civil engineering works, including building information modelling (BIM) – Information management using building information modelling – Part 1: Concepts and principles.
National Standards Authority of Ireland. (2026). Driving digital delivery for Ireland's infrastructure: Raising awareness of the ISO 19650 review and its importance for the Irish BIM Mandate.
National Standards Authority of Ireland. (2026). BIM certification.
Transport Infrastructure Ireland. (2026). BIM for Infrastructure and Information Management in TII.



Comments